Construction Procurement Schedule and Long-Lead Tracker
Track design release, submittal, approval, manufacturing, shipping, delivery, inspection and installation need dates.
Track design release, submittal, approval, manufacturing, shipping, delivery, inspection and installation need dates.

Start from installation dates
Work backwards from the programme to identify required-on-site and order dates.
Include approval cycles
Allow time for samples, technical submittals, revisions and client decisions.

Track commercial status
RFQ, evaluation, budget approval, purchase order and advance payment all affect lead time.
Escalate exceptions
Use a short list of critical late items with owners and recovery actions.
Use this in Build Mart Nepal
Turn the guidance into action by creating a project, loading a BOQ, matching local providers, issuing quotations and storing approvals in the Build Mart Nepal construction operating system.
Quick implementation checklist
- Define the required outcome and acceptance evidence.
- Assign an owner and target date.
- Record quotations, approvals and changes.
- Inspect completed work and retain handover records.
NepalBuild Admin
Content Team · BuildMartNepal.com — Nepal's construction materials marketplace
Similar articles
Construction Project Controls: Schedule, Cost, Quality and Risk
An integrated project-control framework for owners, consultants and contractors managing construction in Nepal.
Checklist for Buying Construction Materials Online in Nepal
Verify specifications, sellers, certification, delivery, payment and inspection before ordering construction products online.
BOQ Basics for Homeowners and Small Contractors in Nepal
Understand BOQ items, units, rates, provisional sums, variations and payment measurements before construction starts.
Construction Quotation Comparison: Price Is Not the Only Number
A practical method for comparing scope, specification, tax, lead time, warranty and exclusions across quotations.